How We Work Engagements → Qualification → Commercial Launchpad → Fractional Director → Commercial Build VR Brands → Aquelon → Dropped → Ringcraft Strategy Hub Sectors → Oil & Gas → Defence & Government → Marine → Rail → Power Generation → Automotive & Heavy Vehicle → Construction & Building Products → Electronics, Instrumentation & Test → Industrial Safety Markets → United Kingdom → Europe & EMEA → UAE & ADNOC → Saudi Arabia → North America → Scandinavia & Nordics → Eastern Europe → Australia & APAC → South America → EPC Strategy About
Book a Call
Client Login
Home/Strategy Hub/Rail and Locomotive Procurement: Getting...
VR Intelligence

Rail and Locomotive Procurement: Getting Designed In Early

Rail and Locomotive Procurement: Getting Designed In Early

Most component manufacturers hear about a locomotive programme once the order's already been placed. By then the engine's chosen, the cooling layout's drawn and the bill of materials is half written. They aren't late to the tender. They're late to the design.

Rail buys in two stages, and almost everyone sells to the wrong one first. I've sold into Progress Rail, EMD and Wabtec, and the pattern holds every time.

Two procurements, not one

The first procurement is the railway or operator buying locomotives or a fleet. The second is the builder buying the components that go into them. Suppliers watch the first, because it's public and it makes headlines. The money for a component maker sits in the second, and the second is mostly decided before the first is signed.

A builder doesn't design a new locomotive for every order. It offers a platform that's already engineered, already qualified and already costed. When an operator buys, it's mostly buying that platform with options. The design conversations that decide whose pump, valve, sensor or gauge goes on it happened while the platform was being developed or updated, often years earlier.

By the time the fleet order's announced, the bill of materials is mostly written. Your job is to be on it before the press release.

Follow the engine, not the locomotive

On a diesel locomotive, a lot of the component decisions flow from the engine. Cooling, filtration, exhaust aftertreatment, mounting and controls all get engineered around it. So the early conversation often isn't with the locomotive line at all. It's with the engine team.

That's where I found my way in. At Gilkes, the engine cooling pump business, the route into rail ran through the engine builders, after marine, on the back of a regulatory change that forced engines to be redesigned. I won't retell the whole story here. The lesson's the bit that matters. The engine team decides first, and everyone downstream inherits that decision.

Regulation sets the calendar

Engineers don't reopen a proven design for fun. Something forces it. In rail that's usually emissions, a new platform, electrification or a fleet coming to the end of its life.

Emissions are the clearest example. The US Environmental Protection Agency has regulated emissions from new and remanufactured locomotives since the 1990s, and its 2008 rule brought in the Tier 3 and Tier 4 standards for locomotive engines and for marine diesel engines below 30 litres per cylinder in the same rulemaking. In my experience every step like that sends engine builders back to the drawing board. Every return to the drawing board is a window, and it doesn't stay open long.

So track the rule changes in the markets you care about. They tell you when the design work will happen, and that's when you need to be in the room.

What getting in early actually looks like

  • Get to the engineers before purchasing. Purchasing buys from the approved list. Engineering shapes the list.
  • Find out where the design freeze sits. Once a design's frozen, every change goes through change control and gets far harder to win.
  • Bring evidence an engineer can defend. Test data, life cycle numbers, failure history, quality documentation. They're putting their name to it for decades.
  • Get qualified in parallel, not afterwards. I covered the quality gates in getting qualified by Progress Rail, EMD and Wabtec.
  • Talk to the operator's engineers too. Railways have strong views on maintenance, depot spares and commonality with the fleet they already run. A builder listens to its customer.

Early is the biggest lever, not the only one

Being designed into the original build tilts the odds hard in your favour. You get the volume, the margin and decades of spares behind it. But it isn't pass or fail.

Plenty of rail business goes to suppliers who were never in the original build. It goes on obsolescence, when the incumbent part reaches end of life. It goes on remanufacture and modernisation, which reopen the design on locomotives already in service. It goes on a second source a builder now wants after a supply shock, and on a sharper commercial case when the incumbent gets comfortable. I went through those doors in Breaking Into Rail.

Getting in early doesn't decide the outcome at a single gate. It means you start every programme with the odds already leaning your way.

Know which platforms are moving

All of this depends on knowing which builders, platforms and fleets are moving before everyone else does. Most manufacturers find out from a trade press story, which is far too late. That's the job Parteloa was built for. It tells you whether a market's worth pursuing, then keeps watching it for the changes that open a window.

Rail isn't right for every manufacturer. The cycle's long and qualification costs real money before the first order lands. If you're weighing up whether rail's worth it for your product, Qualification is a 45 minute call, direct with me, that gives you a straight yes, no or not yet. Book it here, or see how I work in rail.

Sources: Regulations for Emissions from Locomotives, US Environmental Protection Agency, last updated 18 May 2026. Checked 27 November 2026.